Section 58 restrictions

Section 58 restriction is a restriction under the New Roads and Street Works Act 1991 that prevents utility companies digging up the road for a pre-determined period once substantial roadworks carried out by the highway authority have been completed.

Utility companies are notified at least 3 months in advance of these works to give them time to complete any necessary works prior to the substantial roadworks taking place. During the course of the restriction works can only be undertaken with the Authority’s permission and in certain circumstances.

Our current Section 58 notices

Sutton Road, Rochford - USRN: 32200857

Three months advance notice is hereby given that Essex Highways intend to carry out the following substantial works for road purposes.

USRN Road Name Location Description Start Date of works
32200857 Sutton Road, Rochford Carriageway, from o/s No 16/18 to o/s No 104 Machine Surfacing 29/03/2021
Notice Date: 2nd November 2020